On 23 June 2021, the government gazetted four exemption orders[1] that modified the timeline of various events under the Strata Management Act 2013 (“SMA 2013”). These exemption orders come into operation retrospectively from 18 March 2020 and will remain in force until 30 June 2021 (“Exemption Period”).
These Frequently Asked Questions (“FAQs”) simplify the exemptions granted to key stakeholders in strata management, namely, management corporation (“MC”), joint management body (“JMB”) and developer under the SMA 2013. At the outset, it is important to highlight that these exemption orders do not apply or affect any legal proceedings, judgment or awards between 18 March 2020 and 23 June 2021.
Management Corporation
Answer:
The Accounts that need to be filed within the Exemption Period shall be filed by 1 July 2021.
Answer:
The AGM which is supposed to take place during the Exemption Period pursuant to the SMA 2013 shall be convened by 1 July 2021.
Joint Management Body
Answer:
The aforesaid 12-month restriction does not apply to such contacts expiring within the Exemption Period and that the contractual period of such contracts entered within the Exemption Period shall not exceed one month after the AGM is convened.
Answer:
The Accounts that have to be filed within the Exemption Period shall be submitted to the COB latest by 1 July 2021.
Answer:
The AGM that has to take place within the Exemption Period shall be convened by 1 July 2021.
Answer:
Both maintenance account and sinking fund account shall be established by the JMB latest by 1 July 2021.
Answer:
The abovementioned Transfer shall be performed latest by 1 July 2021. In the event that unaudited accounts are handed over, the audited accounts that has to be handed to the MC within the Exemption Period shall be done latest by 1 July 2021.
Developer – Management by developer prior to the establishment of JMB
Answer:
The developer is not required to open a maintenance account and a sinking fund account if the developer’s management period expires within the Exemption Period.
Answer:
The Accounts shall be filed with the COB latest by 1 July 2021 if such filing has not been done within the Exemption Period.
Answer:
Yes, provided that the developer’s management period expires within the Exemption Period. Although the exemption order[1] does not specify the deadline for such handover to be performed, it is advised that the handover should be performed soonest possible to avoid unnecessary dispute between the developer and JMB.
[1] P.U.(A) 274/2021 Strata Management (Exemption to Developer) Order 2021
Answer:
The first AGM of the JMB is to be convened within the Exemption Period and the developer shall convene the first AGM latest by 1 July 2021.
Developer – Management by developer before the first AGM of MC
Answer:
Provided that the preliminary management period expires within the Exemption Period, the contractual period of such maintenance and management of building and common property entered by the developer within the Exemption Period shall not exceed one month after the AGM of MC is convened.
Answer:
The developer shall establish both maintenance account and sinking fund account in the name of the MC latest by 1 July 2021.
Answer:
If the filing of the Accounts was not done during the Exemption Period, 1 July 2021 is the deadline imposed for the Accounts to be filed with the COB.
Answer:
Yes, provided the developer’s management period shall expire within the Exemption Period. Although the exemption order did not specify the deadline for such handover to be performed, it is advised that the handover to be performed at the soonest possible to avoid unnecessary contention between the developer and MC.
Answer:
Provided that the first AGM of the MC is to be convened within the Exemption Period, the developer shall convene the AGM latest by 1 July 2021.
Answer:
Provided that the period of which the deposit needs to be paid fall within the Exemption Period, the developer shall pay the deposit latest by 1 July 2021.
Answer:
Yes, provided that:-
(i) the developer submits an application for the repayment of the common property deposit to the COB within the Exemption Period; and
(ii) the COB is satisfied with the conditions of the common property before the deposit of the common property is refunded to the developer.
For any enquiries, please contact the author :
Mah Mun Yan
Senior Associate
Gan Partnership
E: munyan@ganlaw.my
[1] P.U.(A) 274/2021 Strata Management (Exemption to Developer) Order 2021; P.U.(A) 275/2021 Strata Management (Exemption to Commissioner of Buildings) Order 2021; P.U.(A) 276/2021 Strata Management (Exemption to Management Corporation) Order 2021; and P.U.(A) 277/2021 Strata Management (Exemption to Joint Management Body) Order 2021.
DISCLAIMER: This article is for general information only and should not be relied upon as legal advice. The position stated herein is as at the date of publication on 26 June 2021.